Y

FastFacts Information Service

This information is furnished with the understanding that AMG, LLC is not engaged in rendering legal, accounting, or other professional services. Changes in the law may render this information invalid. Legal advice or other expert assistance should be obtained before acting upon any FastFacts information.

# 1510 - OHIO: MECHANICS' LIEN LAW

The Ohio Mechanics' Lien Law took effect on projects involving real property carrying a general contract date of January 1, 1992 or later. Ohio Revised Code §1311:04-19 gives lessors of equipment or tools statutory rights in perfecting a Mechanics' Lien. The law is intended to minimize the need to file liens by getting claims paid promptly and make liens a more cost effective remedy when necessary.

Two notices are necessary. The Notice of Commencement (NOC), and the Notice of Furnishing (NOF). The latter is your responsibility when renting equipment. The Notice of Commencement is completed by the owners listing: the owner of the property, legal description, contractor, lender, surety, and other information to assist potential lien claimants. The owner is to record the NOC with the County recorder and post it on the job site. The Notice of Furnishing is completed by the subtrade.

To have lien rights you must do the following:

Request in writing the NOC. This should be available from the general contractor and the owner or the subcontractor. You are to receive the NOC within ten days of written request. Make all requests by a method that will provide a receipt (e.g. Certified Mail).

Once you receive the NOC you need to serve an NOF to the owner and general contractor if you do not have a contract with the general contractor. The NOF must be served within 21 days of the first date of work. This notice should also be sent by a method, such as Certified Mail, that will produce a receipt.

The owner and the original contractor have a right to directly pay the claim of any subcontractor or supplier who serves an NOF and set-off this amount against the general or subcontractor who failed to pay the supplier.

The lien filing deadline periods are calculated from the last date of your work on the site. (1 or 2 unit occupied residential - 60 days; commercial, industrial - 75 days; oil and gas - 120 days).

Here is the three step procedure for claiming Mechanics' Liens:

1. Serve of Notice of Furnishing
2. Prepare and file an affidavit of lien with the County Recorder, per the above schedule
3. Serve a copy of affidavit of lien on the owner.

The affidavit of lien must be sworn to by a representative of the claimant with knowledge of the claim, must be notarized and contain the amount due over and above all credits and set-off, a description of the property, and the first and last dates that the claimant provided work and material on the job site. Also required is the name and address of the lien claimant, the person or company who contracted for the claimant's services, and the contracting and fee owners.

The Mechanics' Lien Law requires all lien claimants to serve a copy of the affidavit of lien on all owners of the improved property within 30 days of its being field with the County Recorder. Take the necessary steps to give yourself the right to a Mechanics' Lien. Without following the proper procedures, you will have no rights.

The mechanic's lien law (House Bill 238) became effective January 1, 1992, radically changing the procedures for perfecting mechanic's liens in Ohio. The legislation essentially made Ohio a "notice state" -- requiring that an individual seeking to exercise lien rights must notify the involved parties that he is providing labor or materials to the project.

Shortly after the new mechanic's lien law was enacted, interested parties realized that inadvertent drafting errors were in the bill so "cleanup" legislation was drafted and proposed (Senate Bill 338) to correct these problems.

The most significant recent changes, which should become effective in mid-April, 1993 are as follows:

-- April 1993 (Effective January 1, 1992, Revised April 16, 1993) This summary is provided by Don Gregory of Emens, Kegler, Brown, Hill & Ritter, Attorneys at Law.

Note: For a sample Notice of Furnishing for Private Improvements, click here.

Note: For a sample Notice of Furnishing for Public Improvements, click here.